The Shearon Harris Nuclear Power Plant is a nuclear power plant with a single Westinghouse designed pressurized-water nuclear reactor operated by Duke Energy. It was named in honor of W. Shearon Harris, former president of Carolina Power & Light (predecessor of Progress Energy). Located in New Hill, North Carolina, in the United States, about 20 miles (30 km) southwest of Raleigh, it generates 900 MWe, has a 523-foot (160 m) natural draft cooling tower, and uses Harris Lake for cooling. The reactor achieved criticality in January 1987 and began providing power commercially on May 2 of that year.
The Shearon Harris site was originally designed for four reactors, but cost and weakening demand despite a growing population resulted in three of the reactors being canceled. The final cost approached $3.9B, including safety upgrades mandated after the Three Mile Island accident.
On November 16, 2006, the operator applied to the Nuclear Regulatory Commission (NRC) for a renewal and extension of the plant's operating license. The NRC granted the renewal on December 17, 2008, extending the license from forty years to sixty.
Units 2 & 3Edit
On February 19, 2008 Progress filed an application with the Nuclear Regulatory Commission (NRC) for a Combined Construction and Operating License (COL). It seeks to build two 1,100Â MWe Westinghouse AP1000 pressurized water reactors. Although the NRC has already certified the AP1000 design, the application review is expected to take about 36Â months. The new reactors would not be operational before 2018.
Expansion of the plant will require raising the water level of Harris Lake by 20Â feet, decreasing the size of Wake County's largest park, with the Cape Fear River as a backup water source.
On January 22, 2010 officials at the Nuclear Regulatory Commission announced the electrical generator from the damaged Unit 2 reactor at Three Mile Island will be used at Shearon Harris. The generator was refurbished and installed during a refueling outage in November, 2010.
On May 2, 2013, Duke submitted a request to the NRC to suspend review of the Harris Units 2 and 3 Combined License Application (COLA), effectively halting further development of this project. Duke has determined the forecast operating dates of the proposed reactors falls outside the fifteen-year planning horizon utilized by state regulators in their demonstration of need evaluation. The COLA remains docketed, however, leaving the door open for Duke to restart activities.
Reactor dataEdit
The Shearon Harris Nuclear Power Plant consists of one operational reactor. Three additional units were cancelled. Two new additional reactors are planned.
SafetyEdit
Nuclear Regulatory Commission inspectionsEdit
As of September 2017, the Harris plant is one of three out of the 99 plants in the country to have no Nuclear Regulatory Commission (NRC) findings during the past 4 quarters of inspections.
The NRC's risk estimate for an earthquake intense enough to cause core damage to the reactor at Shearon Harris was 1 in 434,783, according to an NRC study published in August 2010.
Surrounding populationEdit
The Nuclear Regulatory Commission defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of 10 miles (16Â km), concerned primarily with exposure to, and inhalation of, airborne radioactive contamination, and an ingestion pathway zone of about 50 miles (80Â km), concerned primarily with ingestion of food and liquid contaminated by radioactivity.
The 2010 U.S. population within 10 miles (16Â km) of Shearon Harris was 96,401, an increase of 62.6 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within 50 miles (80Â km) was 2,562,573, an increase of 26.0 percent since 2000. Cities within 50 miles include Raleigh (21 miles to city center), Durham (24 miles to city center), Fayetteville (39 miles to city center).
During FEMA's most recent evaluation of state and local government's plans and preparedness included emergency operations for the plant, no deficiencies or areas requiring corrective actions were identified.
NC-WARN concernsEdit
The anti-nuclear group "N.C. Waste Awareness and Reduction Network" (NC-WARN) questioned the facility's safety and security record calling it "insufficient" and claiming "it is the most dangerous nuclear plant in the US". However, the plant's technical and security systems have passed all Nuclear Regulatory Commission (NRC) standards as of 2008, including protection and security, and no worker or area resident has been injured as a result of the plant's operation.
Spent fuel poolsEdit
In 2010, Project Censored, a non-profit, investigative journalism project, ranked the safety issues at Shearon Harris the 4th most under-reported story of the year, because of the risk of fires at what are the largest spent-fuel pools in the country:
Between 1999 and 2003, there were twelve major problems requiring the shutdown of the plant. According to the NRC, the national average for commercial reactors is one shutdown per eighteen months. Congressman David Price (American politician) of North Carolina sent the NRC a report by scientists at MIT and Princeton that pinpointed the waste pools as the biggest risk at the plant. "Spent fuel recently discharged from a reactor could heat up relatively rapidly and catch fire," wrote Bob Alvarez, a former advisor to the Department of Energy and co-author of the report. "The fire could well spread to older fuel. The long-term land contamination consequences of such an event could be significantly worse than Chernobyl."
In August 2007, NCÂ WARN dropped a lawsuit against Progress Energy that was intended to delay or prevent expansion of Shearon Harris, claiming that continuing the legal battle would cost at least $200,000.
ShutdownEdit
On May 16, 2013, Shearon Harris Unit 1 initiated an unplanned shutdown when reviews of ultrasonic data from a refueling outage in spring 2012 determined a 1/4" flaw was inside the 6"-thick Reactor Pressure Vessel Head. The flaw was near the nozzle for a control rod drive mechanism and attributed to primary water stress corrosion cracking, though no actual leakage was detected. Due to high radiation levels, the repairs required robotic aid.
ReferencesEdit
External linksEdit
- Harris Energy and Environmental Center
- NRC treatise on circuit integrity measures, including Shearon Harris
- NRC Public Information regarding the Units 2 & 3 Expansion Proposal
- Nuclear Regulatory Commission approves construction of first nuclear units in 30 years
- INDY News article about local opposition to NRC safety oversight
- http://www.nukeworker.com/pictures/thumbnails-101.html
- Harris 1 â" Quarterly Performance Summary (NRC)